A 20 × 20 ft slab, 4 inches thick, needs 4.94 cubic yards of concrete, or 5.43 cubic yards to order with 10% waste, costing $679 to $1,059 for the concrete alone delivered. A 10 × 10 ft patio at 4 inches needs 62 bags of 80 lb mix, and most patios use 3,000 PSI concrete at 4 inches thick. Below you will find the concrete for every common slab size, the thickness and PSI by use, how much gravel goes under a slab, how much a slab weighs, and answers to the questions people ask most.
How to Use the Concrete Slab Calculator
1. Measure the length and width in feet — measure the forms, not the plan, because the pour is what you pay for.
2. Pick the thickness in inches — 4 inches for a patio or sidewalk, 5 to 6 inches for a driveway or garage.
3. Press Calculate. You get four answers: how many cubic yards of concrete you need, how many bags that is, how much gravel goes under the slab, and how much it will cost — concrete only, and installed. For the full installed cost by slab type, see the Concrete Slab Cost Calculator page.
Concrete Slab Formula — With a Real Example
A slab is a flat box, so its volume is length × width × thickness. Formula: cubic yards = length (ft) × width (ft) × thickness (in ÷ 12) ÷ 27. Then add 10% waste for spillage, uneven subgrade and form bulging. A shorter way to remember it: cubic yards = square feet × thickness (in) ÷ 324, because 12 × 27 = 324.
Real example — a 10 × 10 ft patio, 4 inches thick. Thickness in feet: 4 ÷ 12 = 0.333 ft. Volume: 10 × 10 × 0.333 = 33.3 cubic feet. Cubic yards: 33.3 ÷ 27 = 1.23 cubic yards. Add 10% waste: 1.23 × 1.10 = 1.36 cubic yards to order — round up to 1.50 cubic yards as sold by most ready-mix plants, which sell in half-yard steps. Cost of the concrete only, delivered at $125 to $195 per cubic yard: 1.36 × $125 to $195 = $170 to $265. In bags, that is 1.36 × 45 = 62 bags of 80 lb mix, rounded up, or 82 bags of 60 lb mix and 123 bags of 40 lb mix.
One warning about bag counts: many calculators on the internet show bag counts worked out on the volume WITHOUT waste — 56 bags for this same 10 × 10 slab instead of 62 — and some round the count down instead of up. That is why people run short. On this page, every bag count is worked out on the volume WITH waste, and always rounded up, because you cannot buy part of a bag. A 20 × 20 ft slab at 4 inches needs 245 bags of 80 lb mix with waste, not the 222 or 224 bags that no-waste calculators show.
Concrete for Common Slab Sizes — Cubic Yards, Bags and Cost
The table below is for a standard 4-inch slab, with 10% waste added. Cubic yards to order is the with-waste figure. Bag counts are worked out on the with-waste volume and rounded up. Concrete only is delivered ready-mix at $125 to $195 per cubic yard. One cubic yard covers 81 square feet at 4 inches thick.
Swipe sideways to see the full table →
| Slab size | Cubic yards to order (with 10% waste) | 80 lb bags | 60 lb bags | Concrete only, delivered |
|---|---|---|---|---|
| 10 × 10 ft patio | 1.36 yd³ | 62 bags | 82 bags | $170 – $265 |
| 10 × 20 ft driveway strip | 2.72 yd³ | 123 bags | 163 bags | $340 – $530 |
| 12 × 12 ft shed pad | 1.96 yd³ | 88 bags | 118 bags | $244 – $381 |
| 20 × 20 ft garage | 5.43 yd³ | 245 bags | 326 bags | $679 – $1,059 |
| 24 × 24 ft garage | 7.82 yd³ | 352 bags | 470 bags | $978 – $1,525 |
| 30 × 40 ft house slab | 16.30 yd³ | 734 bags | 978 bags | $2,037 – $3,178 |
For a thicker slab, multiply by the thickness ratio: a 6-inch slab needs 1.5 times the concrete of a 4-inch slab at the same size, and an 8-inch slab needs twice as much. A 20 × 20 ft slab at 6 inches needs 7.41 cubic yards, or 8.15 to order with 10% waste. A 40 × 60 ft house slab at 6 inches needs 44.44 cubic yards, or 48.89 to order with 10% waste. For the full installed cost of each size — $2,400 to $4,800 installed for a 20 × 20 ft garage slab, $18,000 to $27,600 for a 40 × 60 ft house slab — see the Concrete Slab Cost Calculator page.
Slab Thickness and PSI by Use
Thickness is set by the load, not by preference. The building code sets 3.5 inches as the minimum for a slab on grade in habitable space, but most contractors pour 4 inches to leave room for small variations in the base. Use 4,000 PSI with 5 to 7% entrained air for any exterior slab in a freeze-thaw climate — the concrete code actually requires it for exterior residential slabs in freeze-thaw zones. A 3,000 PSI mix is fine for an interior basement slab or a shop floor that never sees salt or freezing.
Swipe sideways to see the full table →
| Slab use | Thickness | PSI | Notes |
|---|---|---|---|
| Patio, sidewalk, shed pad | 4 in | 3,000 | Foot traffic and light use |
| Driveway, garage floor | 5–6 in | 3,500–4,000 | Cars and light trucks, air-entrained 5–7% in freeze-thaw |
| House slab | 6 in | 3,500–4,000 | With 4 in gravel base and 6 mil vapor retarder |
| RV pad, workshop, shop floor | 6–8 in | 4,000–4,500 | Heavy vehicles, #4 rebar grid |
| Commercial floor, heavy equipment | 8 in+ | 4,000–5,000 | Engineered mix design |
Reinforcement does not change the concrete volume in any meaningful way, but it changes how the slab performs: a #4 rebar grid at 18 inches on-center, or welded wire mesh, holds the slab together as it cures and shrinks. Control joints go every 8 to 10 feet for a 4-inch slab, cut at least one-quarter of the slab depth, so the slab cracks where you want it to. Curing: walk on it after 24 to 48 hours, drive on it after 7 days, full strength after 28 days.
How Much Gravel Under a Slab?
The standard answer is 4 inches of compacted gravel under a residential slab. Go to 6 inches under garage floors and driveways that carry vehicles, and to 6 to 8 inches on clay or poorly drained soil. The building code (IRC R506.2.2) calls for a 4-inch base course of clean sand, gravel, crushed stone or crushed concrete under floor slabs that sit below grade, unless the site soil is already free-draining sand and gravel. Extend the gravel 6 to 12 inches beyond the slab on every side, so the edges and the form stakes sit on a supported base.
Gravel volume uses the same formula as concrete: length × width × depth ÷ 27. A 10 × 10 ft patio needs about 1.23 cubic yards of gravel at 4 inches, or 1.36 cubic yards with 10% waste — about 1.9 tons of 3/4-inch crushed stone at 1.4 tons per cubic yard. A 20 × 20 ft slab needs 4.94 cubic yards, or 5.43 with 10% waste, about 7.6 tons. Crushed gravel costs about $35 to $55 per cubic yard, or $25 to $40 per ton. For interior slabs such as house and garage floors, lay a 6-mil polyethylene vapor retarder over the gravel with the seams lapped at least 6 inches, before setting the reinforcement. Driveways, patios and walkways do not need a vapor retarder, but they still need a firm, uniform base — soft spots under a slab turn into cracks.
Swipe sideways to see the full table →
| Slab size | Gravel at 4 in (no waste) | Gravel to order (with 10% waste) | Tons of 3/4 in stone |
|---|---|---|---|
| 10 × 10 ft | 1.23 yd³ | 1.36 yd³ | 1.9 tons |
| 10 × 20 ft | 2.47 yd³ | 2.72 yd³ | 3.8 tons |
| 20 × 20 ft | 4.94 yd³ | 5.43 yd³ | 7.6 tons |
| 30 × 40 ft | 14.81 yd³ | 16.30 yd³ | 22.8 tons |
How Much Does a Concrete Slab Weigh?
Normal-weight concrete weighs 150 lb per cubic foot, or about 4,050 lb per cubic yard, so a 10 × 10 ft slab at 4 inches weighs 4,982 lb, about 2.5 tons. For any other size, see the Concrete Weight Calculator.
Common Mistakes When Calculating a Slab
The most common mistake is ordering the exact volume with no waste — add 10% every time, for spillage, uneven subgrade and form bulging. The second is using bag counts from a calculator that works them out without waste, or rounds them down: always work bags out on the with-waste volume and round up. The third is measuring the plan instead of the forms — the pour is what you pay for, and a form that bowed out by an inch adds concrete. The fourth is pouring on soft ground with no gravel base: 4 inches of compacted gravel is the code minimum for a below-grade house slab, and 6 inches under a driveway. And the fifth is ordering bags for a job that needs a truck: past about 25 bags of 80 lb mix — roughly half a cubic yard — ready-mix is cheaper and far less work. A 20 × 20 ft slab needs 245 bags; nobody mixes that by hand.
Frequently Asked Questions
How much concrete do I need for a slab?
Multiply length × width × thickness, divide by 27 for cubic yards, and add 10% waste. A 10 × 10 ft slab at 4 inches needs 1.23 cubic yards, or 1.36 to order. A 20 × 20 ft slab at 4 inches needs 4.94 cubic yards, or 5.43 to order.
How many bags of concrete do I need for a slab?
At 4 inches thick: a 10 × 10 ft slab needs 62 bags of 80 lb mix, a 20 × 20 ft slab needs 245 bags, and a 30 × 40 ft slab needs 734 bags — all worked out on the with-waste volume and rounded up. For the full bag calculator, see the Concrete Bag Calculator page.
How thick should a concrete slab be?
4 inches for a patio, sidewalk or shed pad, 5 to 6 inches for a driveway or garage floor, and 6 to 8 inches for an RV pad or workshop. The building code minimum is 3.5 inches for a slab on grade in habitable space.
What PSI concrete should I use for a slab?
3,000 PSI for a patio or sidewalk, 3,500 to 4,000 PSI for a driveway or garage floor, and 4,000 PSI or more for an RV pad or heavy use. Use 4,000 PSI with 5 to 7% entrained air for any exterior slab in a freeze-thaw climate.
How much gravel do I need under a concrete slab?
4 inches of compacted gravel as standard, 6 inches under a garage or driveway. A 10 × 10 ft patio needs about 1.36 cubic yards of gravel with waste, and a 20 × 20 ft slab needs 5.43 cubic yards, about 7.6 tons of 3/4-inch crushed stone.
How much does a concrete slab weigh?
Concrete weighs 150 lb per cubic foot, about 4,050 lb per cubic yard. A 10 × 10 ft slab at 4 inches weighs about 2.5 tons, and a 20 × 20 ft slab at 4 inches weighs about 10 tons.
How much does a concrete slab cost?
Concrete only, a 10 × 10 ft slab at 4 inches costs $170 to $265 delivered, and a 20 × 20 ft slab costs $679 to $1,059. Installed, a 20 × 20 ft garage slab costs $2,400 to $4,800. For the full cost by slab type and size, see the Concrete Slab Cost Calculator page.