A concrete footing (also called a footer) costs $5 to $18 per linear foot installed in the US in 2026 for a typical residential strip footing, and the average footing project costs about $750. A 40 ft × 30 ft house footing needs 5.05 cubic yards of concrete — 251 bags of 80 lb mix. Below you will find the cost by footing type, the concrete per linear foot by size, pad footing volumes, the minimum sizes the building code requires, how deep a footing must go, and answers to the questions people ask most. If you searched for a concrete footer calculator, this is the same tool — a footer and a footing are the same thing.
How to Use the Concrete Footing Calculator
It takes less than one minute.
1. Pick the footing type — strip, pad, or round pier.
2. For a strip footing, enter the total run in feet. For a rectangular building, that is the perimeter — 2 × (length + width) — measured along the centreline of the footing, not to the outside of the wall. Add every interior bearing wall, garage return and chimney base: a center bearing wall on a 40 ft building adds 40 feet.
3. Enter the footing width and thickness in inches.
4. For pads, enter the pad size and how many there are.
5. Press Calculate for cubic yards, bags and cost — concrete only, and installed.
Concrete Footing Formula — With a Real Example
Here is the math, step by step. You do not need to remember it — the calculator does it for you. A footing is a rectangular box, so its volume is length × width × thickness. Formula: strip footing (cubic yards) = length (ft) × width (in ÷ 12) × thickness (in ÷ 12) ÷ 27. Pad footing (cubic yards) = width (ft) × length (ft) × thickness (ft) ÷ 27 × number of pads. Round pier footing (cubic yards) = π × radius (ft)² × depth (ft) ÷ 27 × number of piers. Then add waste: 5% for a formed, machine-dug footing, 10% as the default for an earth-formed trench — the excavator bucket is wider than the design width and the trench sides slough, so 10% is a floor, not a ceiling.
Real example — footings for a 40 ft × 30 ft crawlspace foundation, 16 inches wide and 8 inches thick, with three interior pier pads 24 × 24 × 12 inches. Footing run: 2 × (40 + 30) = 140 linear feet. Cross-section: (16 ÷ 12) × (8 ÷ 12) = 1.333 × 0.667 = 0.889 square feet, so 0.889 cubic feet per linear foot. Strip volume: 0.889 × 140 = 124.44 cubic feet. One pad: 2 × 2 × 1 = 4.0 cubic feet. Three pads: 12.0 cubic feet. Total: 124.44 + 12.0 = 136.44 cubic feet. Cubic yards: 136.44 ÷ 27 = 5.05 cubic yards. Add 10% waste: 5.05 × 1.10 = 5.56 cubic yards, rounded up to the next quarter yard = 5.75 cubic yards to order. Cost of the concrete only, delivered at $125 to $195 per cubic yard: 5.75 × $125 to $195 = $719 to $1,121. In bags, that is 5.56 × 45 = 251 bags of 80 lb mix, rounded up. Installed cost at $5 to $18 per linear foot: 140 × $5 to $18 = $700 to $2,520 — the low end is for shallow, narrow footings in low-cost areas, and a 16 × 8 inch footing runs toward the middle of the range.
Keep the strip and the pads separate in the takeoff: each pad is small — a 24 × 24 × 12 inch pad is exactly 4 cubic feet — but eight of them add 32 cubic feet, or 1.19 cubic yards. Do not subtract anything for the wall or stem that will sit on top: the footing is poured first at full width, and the wall is a separate pour. And measure the trench you actually dug, not the one on the plan — a 16-inch trench that came out at 19 inches takes 19% more concrete than you budgeted.
Concrete Footing Cost by Type
There are three footing types, and each one carries a different kind of load. A strip footing runs continuously under a load-bearing wall and is the most common footing in residential construction. A pad footing is a discrete block under a single column, post or pier. A round pier footing is a cylinder, usually poured in a cardboard tube, under a deck post or a column. A stepped footing is a strip footing that steps down in sections on a slope, so it stays at a consistent depth below grade on both the uphill and downhill sides — each step is treated as a separate rectangular section.
Swipe sideways to see the full table →
| Footing type | Typical size | Used for | Concrete per unit |
|---|---|---|---|
| Strip footing | 16–24 in wide × 8–12 in thick | Foundation walls, additions, garages | 0.89–2.00 cu ft per linear foot |
| Pad footing | 24 × 24 in × 12 in thick | Deck posts, columns, piers | 4.00 cu ft per pad |
| Round pier footing | 12 in diameter × 36–48 in deep | Deck posts, columns, round form tube piers | 3.14 cu ft per pier, 4 ft deep |
| Stepped footing | Same section, stepped on a slope | Sloped sites | Each step measured separately |
Installed, a typical residential strip footing costs $5 to $18 per linear foot, including concrete, labor, digging and forms. The national average footing project costs about $750, most homeowners spend $500 to $2,175, and the full range runs $225 to $3,600. Labor alone typically runs $50 to $350 per footing, averaging $150 each. A deeper, wider footing on weak soil can cost several times what a shallow one does.
Strip Footing Concrete per Linear Foot by Size
The table below is concrete per 100 linear feet of strip footing, before waste, with the cost of the concrete only delivered at $125 to $195 per cubic yard. Add 10% waste to the order. The number to carry in your head is the cross-section: a 16 × 8 inch footing is 0.889 square feet, so every linear foot takes 0.889 cubic feet of concrete. Widening it from 16 inches to 20 inches raises the cross-section to 1.111 square feet and the volume by 23% — footing width is the single most expensive dimension on a foundation, which is why the building code tabulates it.
Swipe sideways to see the full table →
| Footing size (width × thickness) | Concrete per linear foot | Cubic yards per 100 ft (no waste) | Cubic yards to order per 100 ft (with 10% waste) | Concrete only, delivered, per 100 ft |
|---|---|---|---|---|
| 12 in × 6 in | 0.500 cu ft | 1.85 yd³ | 2.04 yd³ | $255 – $397 |
| 16 in × 8 in | 0.889 cu ft | 3.29 yd³ | 3.62 yd³ | $453 – $706 |
| 16 in × 12 in | 1.333 cu ft | 4.94 yd³ | 5.43 yd³ | $679 – $1,059 |
| 24 in × 12 in | 2.000 cu ft | 7.41 yd³ | 8.15 yd³ | $1,019 – $1,589 |
For a 40 ft × 30 ft building, the perimeter is 140 feet, so a 16 × 8 inch strip footing needs 4.61 cubic yards before waste, and a 24 × 12 inch footing needs 10.37 cubic yards. If the footing also carries a stem wall above it, calculate each section separately and add them: a 24-inch wide × 10-inch thick footing plus a 10-inch wide × 24-inch tall stem wall, 100 feet long, is 166.7 + 166.7 = 333.4 cubic feet, or 12.35 cubic yards, so order 13 to 14 cubic yards.
Pad Footing Concrete per Pad
Pad footings are sized by the post or column they carry. As a rule of thumb for a wood post, use a pad three times the post width and at least 6 inches thick — for a 6-inch post, that is an 18-inch pad. The actual size depends on the load, so an engineer sizes pads for decks, pergolas and any elevated structure. The table below is per pad, 12 inches thick unless stated, before waste.
Swipe sideways to see the full table →
| Pad size | Concrete per pad | 80 lb bags per pad | Notes |
|---|---|---|---|
| 18 × 18 × 12 in | 2.25 cu ft | 4 bags | For a 6 in post, by the 3× rule |
| 24 × 24 × 12 in | 4.00 cu ft | 7 bags | Standard deck post pad |
| 24 × 24 × 18 in | 6.00 cu ft | 10 bags | Deeper pad, heavier load |
| 36 × 36 × 12 in | 9.00 cu ft | 15 bags | Large column or heavy load |
Six deck pads at 24 × 24 × 12 inches need 6 × 4.0 = 24 cubic feet, or 0.89 cubic yards, and 1.0 cubic yard to order with 10% waste. For a job under 1 cubic yard, bags are usually the practical choice: a ready-mix truck order under about 3 cubic yards often adds a $50 to $150 short-load fee, and a small pad job may not be worth a truck at all. Six pads need 44 bags of 80 lb mix with 10% waste — 26.4 cubic feet ÷ 0.60 — or 59 bags of 60 lb mix.
How Wide, How Thick and How Deep Must a Footing Be?
The International Residential Code (IRC) sets the minimums, and they are a floor, not a recommendation. Minimum footing size — the number a concrete footing size calculator checks first — is 12 inches wide and 6 inches thick. By stories, on soil: a 1-story structure needs 12 inches wide and 6 inches thick, a 2-story structure 15 inches wide and 7 inches thick, and a 3-story structure 23 inches wide and 8 inches thick. The footing must project beyond the face of the wall by at least 2 inches, but not more than the footing thickness. Most contractors pour 16 to 24 inches wide and 8 to 12 inches thick, which fits two #4 bars with 3 inches of cover.
Depth is set by the frost line, not by preference. The footing bottom must sit at least 12 inches below undisturbed ground (IRC §R403.1.4) and below the local frost line (IRC §R403.1.4.1), whichever is deeper. Frost depth is about zero along the Gulf Coast, 12 to 30 inches across the middle of the country, and 42 to 60 inches in the northern states — Chicago is 42 inches, Minnesota 60 inches. Pouring a footing above the frost line is the single most common footing failure in cold climates: even a 2-inch frost-heave cycle will crack it. Never pour a footing on frozen ground — frozen soil expands and thaws underneath, causing differential settlement.
For strength, the concrete code sets 2,500 PSI minimum for footings not exposed to weather and 3,000 PSI for footings exposed to freeze-thaw, so 3,000 PSI is the practical standard for residential footings. For steel, the code requires at least two #4 (1/2 inch) continuous reinforcing bars in footings more than 12 inches thick and in all footings supporting more than one story, and many local codes require rebar in all footings regardless. Even where it is not required, two continuous bars significantly improve crack resistance at relatively low cost. At corners, use L-shaped bars extending at least 24 bar-diameters beyond the corner in each direction — short laps at corners are a common site deficiency.
Common Mistakes When Calculating a Footing
The most common mistake is ignoring the frost depth — check the number with your local building department before you dig, because the code minimum is a floor and your jurisdiction's frost line governs. The second is pouring onto loose or disturbed soil: footings must bear on undisturbed, compacted native soil, not backfilled material, because the bearing capacity of disturbed fill is unpredictable. The third is under-sizing the width by using a rule of thumb such as twice the wall width instead of the code table, which depends on the soil and the number of stories. The fourth is leaving out interior bearing walls, garage returns and chimney bases from the run. The fifth is ordering exactly the calculated volume with no waste — add 5% for a formed footing and 10% for an earth-formed trench, because running short on a footing pour leaves you with a cold joint mid-pour, and ready-mix cannot be returned.
Frequently Asked Questions
How much concrete do I need for a footing?
Multiply length × width × thickness and divide by 27 for cubic yards, then add 10% waste. A 40 ft × 30 ft house with a 16-inch wide, 8-inch thick strip footing and three pier pads needs 5.05 cubic yards, or 5.75 cubic yards to order.
How much does a concrete footing cost?
About $5 to $18 per linear foot installed for a typical residential strip footing. The national average footing project costs about $750, most homeowners spend $500 to $2,175, and the full range is $225 to $3,600.
How deep should a footing be?
The footing bottom must sit at least 12 inches below undisturbed ground and below your local frost line, whichever is deeper. Frost depth is about zero on the Gulf Coast, 12 to 30 inches across the middle of the country, and 42 to 60 inches in the northern states.
How wide should a footing be?
At least 12 inches wide and 6 inches thick. A 1-story structure needs 12 inches wide, a 2-story structure 15 inches, and a 3-story structure 23 inches, on average soil. Most contractors pour 16 to 24 inches wide and 8 to 12 inches thick.
Does a footing need rebar?
The code requires at least two #4 continuous bars in footings more than 12 inches thick and in all footings supporting more than one story, and many local codes require rebar in all footings. Even where it is not required, two continuous bars significantly improve crack resistance.
What PSI concrete is used for footings?
3,000 PSI is the practical standard for residential footings — it meets the 3,000 PSI minimum for footings exposed to freeze-thaw. Footings not exposed to weather need only 2,500 PSI minimum.
How long after pouring can I build on a footing?
Concrete reaches about 70% of its 28-day strength in 7 days. Most contractors begin forming walls above a footing after 3 to 5 days, but full design load should not be applied until the 28-day cure is achieved, typically 4 weeks.